Production crews will bill the same rates as hourly rates of T&E crews if they are performing T&E work. JEA estimates a total of 3,003 Production circuit miles per 2.5-year cycle or roughly 1,200 Production miles per year. The JEA service area is broken up into 3 districts. The districts will be completed simultaneously requiring the Contractor to always have a group of crews in each district. Each district shall have a dedicated General Foreman (GF) responsible for Production crews and their work (three GF’s). Any Production work scheduled within a quarter should be completed in that quarter. Any carryover works not completed by the end of the first month of the following quarter will be subject to liquidated damages, as detailed in the Liquidated Damages section, until the work is completed and verified complete by JEA. These Liquidated Damages will include weekends and holidays.