The Corps of Engineers Norfolk District is soliciting comments from the construction community addressing the potential use of a Project Labor Agreement (PLA) for the following large scale (exceeding $35 Million) construction project: Fuel System Maintenance Dock Hangar – Langley Air Force Base, Hampton, Virginia.
NOTE: This is not an announcement of the availability of a solicitation nor is it a means of generating a plan holder’s list. This survey is for planning purposes only and shall not be constructed as a Request for Proposal or as an obligation on the part of the Government. Responses to this labor market survey will be used by the Government to make appropriate acquisition decisions. All interested sources must respond to future solicitation announcements separately from responses to this market survey. The Government will not contact the responders for clarification of information provided. All information will be held in a confidential manner and will only be used for the purposes intended.
A. PROJECT DESCRIPTION
The new Fuel System Maintenance Dock (Hangar) is a 26,749 SF hangar building that will accommodate two F-22A aircraft for safe concurrent maintenance activities while providing proper clearances throughout the facility. The adjoining administration, storage and utility spaces will provide proper support to the mission. The new facility is to provide a state of the art hangar and support facility with ample amounts of natural day lighting and acoustical design treatments counteracting its close proximity to the flight line. The facility will feature two F-22A maintenance work bays, sheltered in a high bay space, wrapped on three sides by a lower roofed structure for administration, support and utility spaces.
B. PROJECT REQUIREMENTS
The work to be completed under this contract consist of:
C. SUPPLEMENTAL REQUIREMENTS
In accordance with DFARS 236.204, the Magnitude of Construction for this project is between $25,000,000.00 and $100,000,000.00.
The anticipated construction duration is 720 days from the Notice to Proceed (NTP).
PLA is defined a s a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f).
Federal Acquisition Regulation (FAR) policy states: Executive Order (E.O.) 14063, Use of Project Labor Agreement (PLA) for Federal Construction Projects, requires agencies to use Project Labor Agreements in large scale construction projects to promote economy and efficiency in the administration and completion of Federal construction projects.
When awarding a contract in connection with a large-scale construction project (see FAR 22.502), agencies shall require use of Project Labor Agreements every contractor and subcontractor engaged in construction on the project agreement, for that project, to negotiate or become a party to a Project Labor Agreement with one or more labor organization if the agency decides that the use of Project Labor Agreements will:
a. Advance the Federal Government’s interest in achieving economy and efficiency in Federal procurement, producing labor-management stability, and ensuring compliance with laws and regulations governing safety and health, equal employment opportunity, labor and employment standards, and other matters; and
b. Be consistent with law. *
* Reference: FAR Provision 52.222-23 notice of Requirement for Project Labor Agreement and FAR Clause 52.222-34 Project Labor Agreement.
In consideration of the above factors, and any others which may be deemed appropriate, the construction community is invited to comment on the use of a PLA for this construction project.
D. PLA QUESTIONS TO INDUSTRY
In consideration of the above factors, and any others which may be deemed appropriate, the construction community is invited to comment on the use of PLA on this project. Of particular interest to the Government are responses to the following questions:
Additional Questions
The information gathered in this exercise should include the following information on projects completed in the last 205 years:
Please provide your comments via e-mail to Katelyn Vance, Contract Specialist, at [email protected] and copy Nicholas Lizotte, Contracting Officer, at [email protected] no later than 02:00 PM Eastern Daylight Time (EDT) on 10 July 2025.