Federal Contract Opportunity

Last Updated on 12 Jun 2025 at 4 PM
Solicitation
Eielson air force base Alaska

Repair Arctic Utilidor D (FTQW 20-0502) & Utilidor H (FTQW 23-1001)

Details

Solicitation ID 20-0502_23-1001
Posted Date 12 Jun 2025 at 4 PM
Response Date 14 Jul 2025 at 8 PM
NAICS Category
Product Service Code
Set Aside Total Small Business (SBA) Set-Aside (FAR 19.5)
Contracting Office Fa5004 354 Cons Pk
Agency Department Of Defense
Location Eielson air force base Alaska United states 99702

Possible Bidders

National Industries For The Blind

Wayne Earth city Alexandria

Officemax Incorporated

Nashville Charlotte Williston Chesapeake Edwardsville Phoenix Garden grove Naperville Selma Houston Louisville Boise Alexandria Cleveland Hampton Itasca Boca raton Columbus Billerica Menlo park Saint louis Salt lake city Waipahu Warren Orlando Elkridge Carolina Brentwood Maple grove Aurora Pittsburgh Bristol Kent Portland Smyrna Carlstadt Garland

Miscellaneous Foreign Contractors

Frankfurt am main Isando Washington Arlington

Science Applications International Corporation

San antonio King george Sterling heights Colorado sprin Springfield Warner robins Hyattsville Arlington Vista Stafford Fairfield Torrance Bedford Virginia beach El segundo Bothell Buffalo Mystic Herndon Santa monica Whittier San diego Beltsville Panama city beach Austin Washington Lorton Vienna Columbia Mclean Ridgecrest Colorado springs Reston Las vegas Poway North charleston Tampa Santa maria Marietta Middletown Fairfax Chantilly Havelock Annapolis junction Orlando San jose Indianapolis Oak ridge Crane Cookeville Aurora Bellevue El paso O fallon Chambersburg California Hackensack Sterling Huntsville Mc lean Cape canaveral Rosslyn Panama city Fort worth Falls church

Sign up to access Documents

Signup now

The 354th Eielson Contracting Quadron is seeking qualification packages for A&E services for the project below: 

The Arctic Utilidor D & Arctic Utilidor H were constructed and installed in the 1950's and have exceeded their useful life. Many of
the pipes have patches and splices to keep them operational and pipe supports have rusted. In addition, it is suspected there is
significant infiltration and inflow (I&I) entering the system through the utilidor infrastructure due to aging waterproofing and
concrete joint sealing systems. This is causing the wastewater treatment plant to encroach on its permitted treatment volume
during spring break up. Based on previous utilidor projects, it is suspected there will be asbestos-containing material (ACM), but
a hazmat survey shall be conducted for both utilities to determine what hazardous materials are present. Both utilidors fall
within contaminated soils areas. Utilidor D will need the Design of the full-length replacement of all utility systems, this includes
sewer, water, steam, and condensate utility piping in the main utilidor. All lateral lines servicing the Butler Buildings 3435-3442
and Building 3426 shall also be replaced. The existing service to Building 3425 shall remain in place and be connected to the
new utility lines. Utilidor H will also need the full-length design of the replacement of all utility systems, all lateral lines servicing
the buildings shall be replaced. Also design three additional manholes for Utilidor H to provide a maximum of 300-feet spacing
between drip legs and traps.

The contract schedule set forth in the statement of work requires a delivery of 100% design documents in 216 calendar days. 

If this is something your firm is interested in and can accomplish, please submit a combined Instructions to Offers (Evaluation Factors Document), SF330 (Architect-Engineer Qualification-Standard Form 330), and a PPQ (Past Performance Questionnaire).