Repair cracks and spalls on concrete walls, beams, columns, roof, floor slab, and eaves. Repair to
install concrete jackets along column gridlines and roof beams. Repair to restore integrity of
steel members that deteriorated due to corrosion and replace members whose material loss exceeds 10
percent of original thickness. Apply Fiber Reinforced Polymer (FRP) to canopy beams and slabs.
Remove and reinstall electrical and other fixes to facilitate repair works as needed. Paint areas
that are subjected to repair work and restore original appearance. Abate and dispose Asbestos
Containing Material (ACM) and Lead-Based Paint (LBP). Demolish and dispose waste material as
appropriate. Sustainable principles, to include life cycle cost-effective practices, will be
integrated into the design, development, and construction of the project in accordance with UFC
1-200-02.
Construction activities may commence after the approval of the Environmental Protection Plan (EPP)
and AF Form 103 (work clearance). The Contractor shall coordinate on-site safety requirements
through the 718th Civil Engineer Squadron (718 CES).