47--REPLACE INTAKE GATE FLEXIBLE HOSES AT GAVINS POINT PROJECT. QUOTE DUE MAY 12, 2010 BY 3PM. POC CURTIS BISGARD 402-667-2565 OR [email protected]

Solicitation ID W9128F-10-Q-G020
Posted Date 26 Apr 2010 at 1 PM
Archive Date 11 Jul 2010 at 5 AM
NAICS Category
Product Service Code
Set Aside Total Small Business (SBA) Set-Aside (FAR 19.5)
Contracting Office Not Specified
Agency Department Of Defense
Location Crofton Nebraska United states 68730
REPLACE INTAKE GATE FLEXIBLE HOSES AT GAVINS POINT PROJECT. QUOTE DUE MAY 12, 2010 BY 3PM. POC CURTIS BISGARD 402-667-2565 OR [email protected]

INTAKE DECK HYDRAULIC HOSE REHAB
U.S. ARMY CORPS OF ENGINEERS
Gavins Point Power Plant
Yankton, SD

1. General Description of Project. Contractor shall provide all materials, labor, and equipment to rehab 36 hydraulic hoses on the intake deck at the Gavins Point Powerplant near Yankton, SD. DUE TO THE UNUSUAL CIRCUMSTANCES OF THE PROJECT, A PRE-BID SITE VISIT IS STRONGLY ENCOURAGED. THE WORK CANNOT BE PERFORMED CONTINUOUSLY; THEREFORE MULTIPLE TRIPS TO THE POWERPLANT OVER A SEVERAL WEEK PERIOD MAY BE REQUIRED TO ACCOMPLISH THE WORK. Location of Powerplant is actually Cedar County, Nebraska.
2. Existing Equipment. See attached drawings and photos.
3. Scope of Work. This work involves replacing/rehabbing 4 hydraulic hoses on each of 9 hydraulic cylinders. The hydraulic hoses and fittings are 1-1/4 inch and shall be rated for 3000 psi. All materials shall be 304 stainless steel. The o-ring unions shall be 304 stainless steel Hart model 3332 or approved equal. Any welding required shall be performed by a certified pipe welder. All hydraulic hoses shall be exactly the same length and any differences in overall length shall be made up by varying the length of the nipple. Contractor shall conform to the lock-out/tag-out procedures of the US Army Corps of Engineers Hazardous Energy Program. Scheduling of work shall be coordinated through the Powerplant Superintendent.
4. Contract Drawings and Specifications: Omissions from these specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. They shall be performed as if fully and correctly set forth and described in the drawings and specifications.
5. Commencement, Prosecution, and Completion of Work: The Contractor will be required to commence work under this contract on the date of receipt by him of Notice to Proceed, to prosecute said work diligently and to complete the entire work within 90 days. The time stated for completion shall include final cleanup of the premises. The contractor will comply with government work hours, 6:00am - 4:30pm, Monday through Thursday, while working on the government site.
6. Approval of Materials: The USACE shall approve all materials needed before being used in subject contract.
7. Taxes Nebraska.
7.1. Nebraska Sales and Use Tax. Materials installed under this contract are not exempt and the tax must be included in the amount bid. Telephone: (402) 595-2065 (Department of Revenue-Omaha).
7.2. Excise Tax. There is an excise tax on the total gross receipts of all
8. Protection of Existing Facilities: Contractor shall be responsible for protection of the building from any damage that may occur to the building during the construction. Any damage done to the building due to the construction shall be repaired at the cost of the contractor.
9. Environmental Protection: In order to prevent, and to provide for abatement and control of, any environmental pollution arising from the construction activities in the performance of this contract, the Contractor and his sub contractors shall comply with all applicable federal, state and local laws and regulations concerning environmental pollution control and abatement.
10. Safety Requirements: The Contractor shall ensure that safe working practices are in accordance to the requirements of the US Army Corps of Engineers, Safety and Health Requirements Manual, EM 385 1 1, 15 Sept 2008. A copy of the above manual is available at the Gavins Point Project Office, Yankton, South Dakota.
a. Prior to work being started, the contractor shall submit for approval, an Activity Hazard Analysis of all work that is to be performed.
b. Ground Fault Circuit Interrupters: In accordance to the requirements of paragraph 11.D.05 of EM 385 1 1, ground fault circuit interrupters are required for all extension cord systems.
c. First Aid and Medical: First aid facilities shall be made available on the job site. Arrangements for emergency medical attention shall be made prior to start of work. All emergency numbers (doctor, hospital, ambulance, fire department) shall be posted, or made available at the work site.
11. Housekeeping: Daily clean up of all debris and waste materials is required.
12. Debris Disposal: It shall be the contractors responsibility to properly dispose of any removed and un-needed items as well as any construction debris. The Corps reserves the right to keep any components as they see fit.
13. Warranty: Parts and on-site labor shall be warranted for one year for the rehabbed pumps.
14. Place of Performance. Work shall be accomplished on the intake deck of the Gavins Point Power Plant from date of acceptance. THERE ARE NO 220 VOLT OUTLETS AVAILABLE TO RUN WELDERS.
Shipping Address:
US Army Corps of Engineers
Gavins Point Powerplant
55245 Highway 121
Crofton, NE 68730
Mailing Address:
US Army Corps of Engineers
Gavins Point Powerplant
P.O. Box 710
Yankton, SD 57078-0710
POC: Curt Bisgard, Mechanical Engineer
Phone: (402) 667-2565 Fax: 402-667-2537
Alternate POC: Michael Welch, Powerplant Superintendent
Phone: (402) 667-2510
15. Site Visit. Due to unusual site conditions, a site visit is strongly encouraged and can be arranged by contacting one of the above-mentioned individuals.
16. Best Value Bidding Information. Bidders shall be evaluated on a best value basis using the factors listed below. The first two factors, when combined, are considered to be more important than price.
a. Experience in welding 3000 psi hydraulic piping.
b. History of similar projects with the names and contact information of three references we can contact.
c. Price

Gavins Point Project
Intake Deck Hydraulic Hose Rehab

1. Experience and certification in welding 3000 psi stainless steel hydraulic piping. Please provide information on a separate sheet.
2. History of similar projects with the names and contact information of three references we can contact. Please provide information on a separate sheet.
3. Price $______________________
Bid Protests Not Available