Point Of Contact Not Available
Work consists of complete removal of an estimated 13,130 square feet of walking surface to include mostly brick pavers, uneven asphalt trail connection points and sinking concrete slab at all three campuses and replace with 6-inch-thick reinforced solid colored concrete. Replace 1800 square feet brick paver octagon shaped fire circle with concrete rebuild benches. Add new sidewalk with curb along roadway measuring 5 feet wide by 535 feet long estimated 2675 square feet. Replace steps and landings, repair or replace downspout drainage, replace handrails at all three campuses, replace wooded deck and concrete pad on second story ADA ramp, replace lighting bollard shells, repair retaining wall, install trough drains, remove trees and install ADA warning pads per regulation. Contractor responsible for verifying all measurements and quantities before ordering material.