Point Of Contact Not Available
Brazoria County is seeking bids for drainage improvements and a ADA sidewalk at Hanson Riverside Park. The work for the parking lot area generally consists of saw cutting 74 feet and removal of a 12" wide strip of asphalt for smooth connection, 1,441 S.F. of asphalt overlay to direct flow to inlets, 162 feet of 10", 12" and 15" Storm Sewer, 3 Type “A” inlets, 271 feet of doweled on concrete curb and other miscellaneous work detailed in the plans. The work for the walkway area generally consists of removal of a crushed granite walkway, borrow for sidewalk embankment, 1,490 S.F. of 6' wide concrete sidewalk, seeding and other miscellaneous work detailed in the plans.