RECOVERY: The purpose of this modification to TASK ORDER IBM09T0019 is to re-establish benchmark for the construction of Hidalgo Phase 2 Construction. The total amount of the change order is a Not to Exceed amount of $2,000 for a total TO amount of $55,075.00. Definitization of this Task Order under RFP 10-20 is anticipated by Feb 15, 2010.
THIS NOTICE IS PROVIDED FOR INFORMATION PLANNING PURPOSES ONLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO THE CONTRACTOR UNDER THE ARCHITECT ENGINEERING SERVICE INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) CONTRACT NUMBER IBM05D0001 WITH S&B INFRASTRUCTURE, LTD.
THE RESULTING NEGOTIATED TASK ORDER WILL BE SYNOPSIZED AND ISSUED UNDER THE PREVIOUSLY COMPETED AND EXISTING FIRM FIXED PRICE SINGLE AWARD IDIQ A/E CONTRACT REFERENCED ABOVE.