FY23 Basic Multiple Award Construction Contract SABER requirements
Amendment 1 dated 2 February 2023 - Cleaned up administrative issues in Section L and Section M. No changes were made, removed red lines and comments.
Amendment 2 dated 6 February 2023 - A site visit will be held for the seed project for this IDIQ on 13 February 2023 at 1.pm. CST. If you need help gaining base access, please email Logan Hamm [email protected] by Friday, 10 February 2023 for the additional information that we will need.
The seed project Magnitude of Construction is between $750K and $1M.
Amendment 3 dated 10 February 2023 - See updated attachment for Questions and Answers, updates to SOW, Section L and Section M.
Amendment 4 dated 21 February 2023 - See updated Attachment 15, Section M, Evaluation of Offerors, updated Attachment 14, Section L, Instructions to Offerors and Attachment 21, Questions and Answers Set # 2. Attachment 20 Asbestos Report for the seed project, Roof Repair at B72, is now available.
As builts for the seed project, Roof Repair at B72 are available by contacting Logan Hamm at [email protected] and requesting a DOD safe drop off link.
All questions are due by 22 February 2023 at 11:00 a.m. CST per Attachment 14, Section L, 10
Amendment 5 dated 24 February 2023 - See updated Attachment 15, Section M, Evaluation of Offerors, updated Attachment 14, Section L, Instructions to Offerors, Updated Attachment 1 MACC SABER SOW dated 24 February, Updated Response date on Solicitation SF1442, and Attachment 22, Questions and Answers Set #3.
This Amendment extends the proposal due date to 10 March 2023 at 11:00 am. CST.
Amendment 6 dated 2 March 2023 - See updated Attachment 15, Section M, Evaluation of Offerors, updated Attachment 14, Section L, Instructions to Offerors, Updated Response date on Solicitation SF1442 and added clauses 52.228-5 Insurance – Work on a Government Installation, and 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts, and Attachment 23-Questions and Answers Set 4.
This Amendment extends the proposal due date to 17 March 2023 at 11:00 am. CST.