AMENDMENT 01 IS ISSUED TO:
1. POST THE RESPONSE TO A QUESTION FROM A VENDOR FOR ALL TO VIEW
2. EXTEND THE CLOSING DATE TO MONDAY, JANUARY 13, 2013
VENDOR QUESTION:
"In order to submit a quote, I need to have some type of estimate on how many days or hours this survey will include. The statement of work only states the survey will occur during the months of March and April 2014".
RESPONSE:
We are expected to complete 15 days of survey. We generally assume 1 rest day for every 5 survey days. There will also be 1 travel day when moving the survey between Guam and Saipan.