Project will include removal of road surfacing at two sites; removal of two existing culverts on Forest Road 16 at Little Crane Creek (and removal from Forest Service land); furnish and installation of open bottom, aluminum box culverts at Halfway Creek and Little Crane Creek, including placing a concrete slurry in the inside footing trenches; placement of a temporary diversion culvert at the Little Crane Creek location; removal of temporary diversion culvert and permanent placement at a higher elevation; building an animal exclosure fence at the Halfway Creek site; and road restoration which involves road widening, building a superelevated curve, and placement of cold mix. Instream work in Little Crane Creek is restricted to July 1 through July 22, 2003; work for Halfway Creek and other work items at Little Crane Creek is restricted to July 1 through August 31, 2003. This project is estimated between $25,000 and $100,000. Contract time is 45 days with an estimated start work date of July 7, 2003.